Question: Consider two activities (X and Y) appearing in the Work Breakdown Structure. X refers to a programmer writing code for an application program. Y refers

Consider two activities (X and Y) appearing in the Work Breakdown Structure. X refers to a programmer writing code for an application program. Y refers to a user testing that program. If prototyping is used, the programmer may begin with a simplified version that allows the user to do limited testing. Based on the results of that limited testing, the programmer can then refine the program and add more functionality, followed by the user doing further testing. Activity X is completed when the programmer has finished the program. Activity Y is finished when the user has finished testing the program. Which one of the following best describes the task dependency types relationship from X to Y?

a.

Finish to start

b.

Start to start

c.

Finish to finish

d.

Both start to start and finish to finish

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!