Question: Consider two periodic processes, P1 and P2, where p1 = 50, t1 = 25, p2 = 100, and t2 = 40. A - Can these
Consider two periodic processes, P1 and P2, where p1 = 50, t1 = 25, p2 = 100, and t2 = 40.
A - Can these two processes be scheduled using rate-monotonic scheduling? Illustrate your answer using a Gantt chart.
B - Illustrate the scheduling of these two processes using earliest deadline-first (EDF) scheduling.