Question: Consider two projects, A and B. Project A's first cash flow is $9,100 and is received three years from today. Future cash flows for Project
Consider two projects, A and B. Project A's first cash flow is $9,100 and is received three years from today. Future cash flows for Project A grow by 4 percent in perpetuity. Project B's first cash flow is $9,800, which occurs two years from today, and will continue in perpetuity. Assume that the appropriate discount rate is 12 percent.
a. What is the present value of each project?
b. Suppose that the two projects are combined into one project, called C. What is the IRR of Project C?