Question: Consider two Tasks T1 and T2, with their processing time t, deadline d, and period p (t, d. p) given as (20. 40. 40) and
Consider two Tasks T1 and T2, with their processing time t, deadline d, and period p (t, d. p) given as (20. 40. 40) and (25, 65, 65), respectively. Illustrate the scheduling of these two tasks using rate monotonic (RM) and earliest-deadline-first (EDF) scheduling Show the Gantt chart of the scheduling order. a RM Gantt Chart b. EDF Gantt Chart