Question: Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method).

Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method). The actual progress and cost are recorded at the end of 15th week.

activity

Duration(week)

cost

completed

Actual cost

Immediate successors

1

4

10

100%

18

2,5

2

7

30

100%

26

3,4,7

3

2

36

100%

48

6

4

6

80

50%

60

6

5

3

46

100%

52

6

6

9

60

0%

0

8,10

7

3

20

10%

10

8,10

8

10

90

0%

0

9

9

9

72

0%

0

10

6

55

0%

0

  1. Give the cumulative planned value of each week.
  2. According to the actual progress and cost data, calculate the SV, SPI, CV, CPI , and explain the meaning of these indicators.
  3. According to the actual progress data, calculate the ES, SV(t), SPI(t), and explain the meaning of these indicators.

Step by Step Solution

3.56 Rating (146 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The following formula is used to calculate the cumulative planned value for each week b Cumulative ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!