Question: Activity Immediate Pred Optimistic Most Likely Pessimistic A None 2 3 6 B None 3 5 6 C A 2 6 10 D A 5
Activity | Immediate | Optimistic | Most | Pessimistic |
A | None | 2 | 3 | 6 |
B | None | 3 | 5 | 6 |
C | A | 2 | 6 | 10 |
D | A | 5 | 8 | 9 |
E | B,D | 8 | 10 | 13 |
F | B,D | 1 | 4 | 6 |
G | C,E | 5 | 7 | 11 |
H | C,E | 3 | 3 | 3 |
I | F,H | 2 | 2 | 4 |
J | G | 6 | 8 | 13 |
K | I,J | 4 | 5 | 7 |
1. Construct the network for this project and,
2. Calculate the ES, LS, EF, LF, and Slack for each activity of the project?
3. What is the probability that the project will be completed in 3 DAYS?
Step by Step Solution
3.42 Rating (152 Votes )
There are 3 Steps involved in it
1 PERT Network diagram 33 D 109 97 13 76 206 33 E 134 49 0A 33 49 49 33 82 134 I 157 49 183 23 206 8... View full answer
Get step-by-step solutions from verified subject matter experts
