Activity Immediate Pred Optimistic Most Likely Pessimistic A None 2 3 6 B None 3 5 6
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity | Immediate | Optimistic | Most | Pessimistic |
A | None | 2 | 3 | 6 |
B | None | 3 | 5 | 6 |
C | A | 2 | 6 | 10 |
D | A | 5 | 8 | 9 |
E | B,D | 8 | 10 | 13 |
F | B,D | 1 | 4 | 6 |
G | C,E | 5 | 7 | 11 |
H | C,E | 3 | 3 | 3 |
I | F,H | 2 | 2 | 4 |
J | G | 6 | 8 | 13 |
K | I,J | 4 | 5 | 7 |
1. Construct the network for this project and,
2. Calculate the ES, LS, EF, LF, and Slack for each activity of the project?
3. What is the probability that the project will be completed in 3 DAYS?