Question: Considering the given information in the activity dependency table below 1. Daw the Activity-on-Node (ADN) network 2. Carry out network calculations and find the project

Considering the given information in the activity

Considering the given information in the activity dependency table below 1. Daw the Activity-on-Node (ADN) network 2. Carry out network calculations and find the project duration. 3. Calculate Early/Late Start and Early/Late Finish and Total Float for all activities by filling in the below table Project Completion Time: Activity Name Duration Predecessor(s) Early Start Early Finish Late Start Late Finish Total Float A 2 B 5 C 2 D 3 B " E 9 B F. 7 B,C " " G 3 A H 9 AD 1 4 A, D, E, F