Question: Constraint 1 Constraint 2 Constraint 3 Constraint 4 Constraint 5 A firm has prepared the following binary integer program to evaluate a number of potential
Constraint 1
Constraint 2
Constraint 3
Constraint 4
Constraint 5
A firm has prepared the following binary integer program to evaluate a number of potential locations for new warehouses. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital. Max 20x1 + 30x2 + 10x3 + 15x4 s.t. 5x1 + 7x2 + 12x3 + 11x4 = 21 (Constraint 1) x1 + x2 + x3 + x4 ? 2 (Constraint 2) x1 + x2 > 1 (Constraint 3) x1 + x3 = 1 {Constraint 4) x2 = x4 (Constraint 5) 1, if location j is selected X; = 0, otherwise Which of the constraints enforces a contingent relationshipStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock