Question: Constraints include labels and appropriate dimensional analysis ( 1 1 pts each constraint ) - Aidan: X 1 1 + X 1 2 + X

Constraints include labels and appropriate dimensional analysis (11 pts each constraint)
- Aidan: X11+ X12+ X13<=176
- Max: X21+ X22+ X23<=176
- Elena: X31+ X32+ X33<=136
- Client (1): X11+ X21+ X31=190
- Client (2): X12+ X22+ X32=125
- Client (3): X13+ X23+ X33=160
- Non Negativity: Xij >=0 for all i and j.
Put your problem above into solver and solve it.(50 pts) Include your answer and sensitivity reports as usual. (2 pts.)
Answer the following questions:
How many hours will each consultant work for each client? (27 pts. make sure to label and not just give numbers)
What is the total amount the company can bill if all three proposals are accepted?
What is the amount that will be cited for the project cost in each proposal? (Hint: Who is working for that client, what is the billing rate and the total hours the employee(s) will work for the client if the proposal is accepted. You can figure out the amount put in the proposal from that information.)
Will any of the consultants have slack or surplus hours? (will it be slack or surplus and why 2 pts.) In other words, will there be a consultant who will not be assigned billable time during the month of April even though available to work those hours? (1 pt.) Who is it and how many hours will they be lacking billable work? (2 pts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!