Question: Construct a Man Machine Chart / Multiple Activity Chart for doing 3 loads of laundry, assume you will have access to one washing machine and
Construct a Man Machine Chart / Multiple Activity Chart for doing 3 loads of laundry, assume you will have access to one washing machine and one dryer. Consider the following time for constructing the chart:
Loading clothes in Washing machine 2 minutes
Washing time 5 minutes
Unloading clothes from washing machine 1 minute
Loading clothes in dryer 1 minute
Drying time 3 minutes
Unloading clothes from dryer 1 minute
Note: Use Microsoft Excel to construct the chart