Question: Construct a Man Machine Chart / Multiple Activity Chart for doing 3 loads of laundry, assume you will have access to one washing machine and

Construct a Man Machine Chart / Multiple Activity Chart for doing 3 loads of laundry, assume you will have access to one washing machine and one dryer. Consider the following time for constructing the chart:

Loading clothes in Washing machine 2 minutes

Washing time 5 minutes

Unloading clothes from washing machine 1 minute

Loading clothes in dryer 1 minute

Give the summary, which needs to highlight the idle time, percentage of ide time, working time and percentage of working time for:

(a) Operator

(b) Washing machine and

(c) Drying machine

Drying time 3 minutes

Unloading clothes from dryer 1 minute

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!