Question: Construct a Man Machine Chart / Multiple Activity Chart for doing 3 loads of laundry, assume you will have access to one washing machine and
Construct a Man Machine Chart / Multiple Activity Chart for doing 3 loads of laundry, assume you will have access to one washing machine and one dryer. Consider the following time for constructing the chart:
Loading clothes in Washing machine 2 minutes
Washing time 5 minutes
Unloading clothes from washing machine 1 minute
Loading clothes in dryer 1 minute
Give the summary, which needs to highlight the idle time, percentage of ide time, working time and percentage of working time for:
(a) Operator
(b) Washing machine and
(c) Drying machine
Drying time 3 minutes
Unloading clothes from dryer 1 minute
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts