Question: Construct a network diagram for the information provided and identify the critical path in the network. [3] Page 2 of 2 Activity Immediate Predecessors Estimated

Construct a network diagram for the information provided and identify the critical path in the network. [3] Page 2 of 2 Activity Immediate Predecessors Estimated Time in weeks Crash Time in weeks Normal Cost (in INR) Crash Cost (in INR) A - 2 1 180000 280000 B A 4 2 320000 420000 C B 10 7 620000 860000 D C 6 4 260000 340000 E C 4 3 410000 570000 F E 5 3 180000 260000 G D 7 4 900000 1020000 H E & G 9 6 200000 380000 I C 7 5 210000 270000 J F & I 8 6 430000 490000 K J 4 3 160000 200000 L J 5 3 250000 350000 M H 2 1 100000 200000 N K & L 6 3 330000 510000