Question: Construct a network diagram schedule using the precedent diagram method ( activity on the arrow ) . Complete a forward pass to calculate the project
Construct a network diagram schedule using the precedent diagram method activity on the arrow Complete a forward pass to calculate the project completion time. Your schedule should show:
Tasks on arrows with durations
Nodes with running times
Start node with time zero
Finish node with the projects time completiontableTaskPredecessor,DurationABACADBEBFCGDHDIEJFKGLH I, JMF