Question: table [ [ Task , Predecessor,Duration ] , [ A , , 9 ] , [ B , A , 1 6 ] ,

\table[[Task,Predecessor,Duration],[A,,9],[B,A,16],[C,A,10],[D,C,6],[E,B,12],[F,B,12],[G,E,10],[H,F,7],[I,D,3]]Exercise 6-2 Critical Path Method Directions Construct a network diagram schedule using the critical path method (activity on the node). Complete a forward and backward pass to calculate start and finish dates, float, and the critical path. Your schedule should show: Tasks on nodes Task early start and finish, late start and finish, and float Project critical path TCM 651/551
 \table[[Task,Predecessor,Duration],[A,,9],[B,A,16],[C,A,10],[D,C,6],[E,B,12],[F,B,12],[G,E,10],[H,F,7],[I,D,3]]Exercise 6-2 Critical Path Method Directions Construct a network diagram schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!