Question: Construct a PERT/CPM network for project having the following activities; ------------------------------------------------------------------------------------------------ Activities Leads Time/ Labor Activities Weeks ------------------------------------------------------------------------------------------------ A - 3 10 B - 2
- Construct a PERT/CPM network for project having the following activities;
------------------------------------------------------------------------------------------------
Activities Leads Time/ Labor
Activities Weeks
------------------------------------------------------------------------------------------------
A - 3 10
B - 2 9
C - 2 7
D A 4 9
E B 2 6
F B 1 10
G C 2 4
H D,E 2 6
I G 3 6
J D,E 3 6
K F,G,H 2 7
L G 1 6
M L 2 5
- How long will be taken to complete this project?
- Identify the critical path and slack for every activity.
- Compare the weekly labor with Earlier Start (ES), Earlier Finish (EF) and Last Start (LS), Last Finish (LF).