Question: Construct a PERT/CPM network for project having the following activities; ------------------------------------------------------------------------------------------------ Activities Leads Time/ Labor Activities Weeks ------------------------------------------------------------------------------------------------ A - 3 10 B - 2

  1. Construct a PERT/CPM network for project having the following activities;

------------------------------------------------------------------------------------------------

Activities Leads Time/ Labor

Activities Weeks

------------------------------------------------------------------------------------------------

A - 3 10

B - 2 9

C - 2 7

D A 4 9

E B 2 6

F B 1 10

G C 2 4

H D,E 2 6

I G 3 6

J D,E 3 6

K F,G,H 2 7

L G 1 6

M L 2 5

  1. How long will be taken to complete this project?

  1. Identify the critical path and slack for every activity.

  1. Compare the weekly labor with Earlier Start (ES), Earlier Finish (EF) and Last Start (LS), Last Finish (LF).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!