Question: Construct a precedence network based on the activity description below. Label activities in the network by their activity letters. Remove any redundant dependencies. Activity A

Construct a precedence network based on the activity description below. Label activities in the
network by their activity letters. Remove any redundant dependencies.
Activity A and B start the project. A takes 3 days to complete, B takes 4.
The start of Activity C follows the start of A by 2 days and is completed 3 days after the
completion of B. C has a duration of 5 days.
Activity D follows the completion of A and takes 3 days.
The start of E happens 3 days after the completion of D and 2 days after the start of C. The
duration of E is 2 days.
Activities F and G have E as a predecessor and take 3 days each to complete.
Activity H can start 2 days after the completion of F, and 5 days after the start of E. H has a
duration of 1.
The start of Activity J follows the completion of H by 1 day and takes 4 days to complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!