Question: Construct a project network for the activities listed below. Immediate Activity Predecessor(s) A B C B D A E C F D G E, F

Construct a project network for the activities listed below.

Immediate
Activity Predecessor(s)

A

B

C

B

D

A

E

C

F

D

G

E, F

H

E

Choose the correct network for the project. Note that I is a dummy activity.

The correct network is -Select-network Anetwork Bnetwork Cnetwork DItem 1 .