Question: Construct a project network with the following precedence relationships: Activity Immediate Successor Duration A B,C 8 B D 12 C D, E 10 D F
Construct a project network with the following precedence relationships:
| Activity | Immediate Successor | Duration |
| A | B,C | 8 |
| B | D | 12 |
| C | D, E | 10 |
| D | F | 6 |
| E | F | 5 |
| F | - | 4 |
- Find the critical path of this project.
- If the duration of activity B is reduced to 3 days, what is the effect on the critical path?