Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A B C D A, B E B F C, E G D,

A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A B C D A, B E B F C, E G D, E H F, G Draw the network diagram and submit its picture file.