Question: Construct an activity network diagram using Table 3a. (5marks) Activity A B C D E F G Predecessors - - A A,B D C,E E

Construct an activity network diagram using Table 3a. (5marks) Activity A B C D E F G Predecessors - - A A,B D C,E E Expected Time(WKS) 7 9 12 8 9 6 5.

Conduct a forward and backwards pass for the activity network diagram that you

have constructed and identify the critical path and its duration. (10 Marks)

ii. Calculate the slack on all of the activities, and proceed to analyze how knowing the slacks can help to manage schedule risk the a project (10Marks)

3b. Assuming that there is the risk of exceeding the project schedule baseline for 7 weeks, critically evaluates the options available that could be used to bring the project on track

(5 marks).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!