Question: Construct an activity network for the activities in Table 1(d). Assuming the projects starts on day 0, draw out the WBS and Gannt chart. Clearly

  1. Construct an activity network for the activities in Table 1(d). Assuming the projects starts on day 0, draw out the WBS and Gannt chart. Clearly identify the earliest start and latest finish dates for all activities, and the projects earliest completion date.

Task

Duration

Dependency

Resources

A

6

2

B

5

3

C

4

A

3

D

3

B,C

2

E

6

D

2

F

2

C

4

G

5

D

2

H

2

E,G,F

1

Table 1(d)

  1. Use the network to identify the critical path, in table 1(d). Why is this the critical path?
  2. Construct a resource chart from the information in Table 1(d).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!