Question: Construct an activity network for the activities in Table 1(d). Assuming the projects starts on day 0, draw out the WBS and Gannt chart. Clearly
- Construct an activity network for the activities in Table 1(d). Assuming the projects starts on day 0, draw out the WBS and Gannt chart. Clearly identify the earliest start and latest finish dates for all activities, and the projects earliest completion date.
| Task | Duration | Dependency | Resources |
| A | 6 |
| 2 |
| B | 5 |
| 3 |
| C | 4 | A | 3 |
| D | 3 | B,C | 2 |
| E | 6 | D | 2 |
| F | 2 | C | 4 |
| G | 5 | D | 2 |
| H | 2 | E,G,F | 1 |
Table 1(d)
- Use the network to identify the critical path, in table 1(d). Why is this the critical path?
- Construct a resource chart from the information in Table 1(d).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts