Question: d ) Construct an activity network for the activities in Table 1 ( d ) . Assuming the projects starts on day 0 , draw

d) Construct an activity network for the activities in Table 1(d). Assuming the projects starts on day 0, draw out the WBS and Ganntt chart. Clearly identify the earliest start and latest finish dates for all activities, and the project's earliest completion date.
\table[[Task,Duration,Dependency,Resources],[A,7,,2],[B,3,,3],[C,6,A,4],[D,3,A,2],[E,5,D,F,3],[F,2,B,4],[G,4,C,2],[H,2,E,G,1]]
 d) Construct an activity network for the activities in Table 1(d).