Question: Construct an activity - on - branch network from the precedence relationships of activities in the project given in the following Tables. Also calculate critical

Construct an activity-on-branch network from the precedence relationships of activities in
the project given in the following Tables.
Also calculate critical path, EST and LFT values for each event and verify floats using
spread sheet. Also check your critical path (calculated from the network diagram & from
floats spread sheet table).
Activity Description Predecessors Duration
A Preliminary design ----3
B Evaluation of design ----6
C Contact negotiations ----2
D Preparation of fabrication plant C 3
E Final design C 8
F Fabrication of Product B, E 5
G Shipment of the Product to owner A, F 7
H Field inspection of the Product B, E 10
I Installation of the Product B, E 6
J Field painting B, E 6
K Substantial completion D, J 8
L Punch list items completion G, H 3
M Commissioning I, K, L 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!