Question: Construct the activity network based on Activity - On - Node and identify the critical path to estimate the project duration ( minimum days to

Construct the activity network based on Activity - On-Node and identify the critical path to estimate the project duration (minimum days to complete the project). Obtain the Earliest Start, Earliest Finish, Latest Start, Latest Finish and Float value on performing forward and backward pass.
\table[[Activity Name,\table[[Duration],[(Days)]],Precedence],[A,9,-],[B,1,A],[C,10,A],[P,10,A],[L,2,B,C],[F,10,C,P],[Q,8,P],[N,6,P],[Y,7,L],[T,4,F,L],[R,9,F,Q],[S,1,N,Q],[V,10,Y,T,R],[U,1,V,S],[,,]]