Question: Construct the activity network based on Activity - On - Node and identify the critical path to estimate the project duration ( minimum days to
Construct the activity network based on Activity OnNode and identify the critical path to estimate the project duration minimum days to complete the project Obtain the Earliest Start, Earliest Finish, Latest Start, Latest Finish and Float value on performing forward and backward pass.
tableActivity Name,tableDurationDaysPrecedenceABACAPALBCFCPQPNPYLTFLRFQSNQVYTRUVS
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
