Question: Construct the following network and determine the minimum total cost to complete the project if indirect cost is Rs.1500 per day. (kindly show using LS,LF,ES,EF)

  1. Construct the following network and determine the minimum total cost to complete the project if indirect cost is Rs.1500 per day. (kindly show using LS,LF,ES,EF)

Activity

NT

CT

NC

CC

1-2

6

4

6000

7800

1-3

7

4

3000

4200

2-3

4

1

5000

9200

2-5

6

5

6000

7500

3-4

7

3

2000

6800

4-5

3

1

2000

4000

4-6

7

3

4000

5600

5-6

5

4

3000

4100