Question: Construct the following network(AOA) and determine the minimum total cost to complete the project if indirect cost is Rs.1500 per day. Activity NT CT NC
Construct the following network(AOA) and determine the minimum total cost to complete the project if indirect cost is Rs.1500 per day.
| Activity | NT | CT | NC | CC |
| 1-2 | 6 | 4 | 6000 | 7800 |
| 1-3 | 7 | 4 | 3000 | 4200 |
| 2-3 | 4 | 1 | 5000 | 9200 |
| 2-5 | 6 | 5 | 6000 | 7500 |
| 3-4 | 7 | 3 | 2000 | 6800 |
| 4-5 | 3 | 1 | 2000 | 4000 |
| 4-6 | 7 | 3 | 4000 | 5600 |
| 5-6 | 5 | 4 | 3000 | 4100 |