Question: Construct the material requirements plan for item C (enter your responses as whole numbers). Construct the material requirements plan for item C (enter your responses

Construct the material requirements plan for item C (enter your responses as whole numbers).

Construct the material requirements plan for item

Construct the material requirements plan for item C (enter your responses as whole numbers). Item C: Lead Time = 1 week; Minimum order quantity = 300 Week 1 2 3 4 5 6 0 800 500 700 700 700 0 600 100 400 200 0 Gross requirements Scheduled receipts Projected ending inventory: 350 Net requirements Planned receipts 350 150 0 0 0 800 O O 0 800 Enter your answer in the edit fields and then click Check