Question: Please help with numbers NOT grayed out. The numbers in white boxes are incorrect. Please show work. Construct the material requirements plan for item C

Please help with numbers NOT grayed out. The numbers in white boxes are incorrect. Please show work.

Please help with numbers NOT grayed out. The

Construct the material requirements plan for item C (enter your responses as whole numbers). Item C: Lead Time = 1 week; Minimum order quantity = 900 Week 1 2 3 5 6 0 1000 700 300 700 100 250 200 0 Gross requirements Scheduled receipts Projected ending inventory: 300 Net requirements Planned receipts 0 300 450 0 700 500 ol 0 0 700 100 300 700 0 700 700 100 300