Question: Construct the material requirements plan for item Speakers (enter your responses as whole numbers). Construct the material requirements plan for item CD-ROMs (enter your responses

 Construct the material requirements plan for item Speakers (enter your responses

Construct the material requirements plan for item Speakers (enter your responses as whole numbers).

Construct the material requirements plan for item CD-ROMs (enter your responses as whole numbers).

as whole numbers). Construct the material requirements plan for item CD-ROMs (enter

Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information Production plans for complete kits are as follows Start assembling 5,500 kits in week 2 Start assembling 4,000 kits in weeks 3, 4, and 5 Start assembling 16,500 kits in week 6 The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements All scheduled receipts, lead times, and beginning inventory levels are shown. EB Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers) System unit: Lead Time (weeks)-1 Week Gross requirements Scheduled receipts Projected ending inventory: 8000 INet requirements Planned receipts Planned orders Minimum order qty 16,500 5,500 4,000 4,000 4,000 16,500! iSpeakers: Lead Time- 11 Weeks Minimum order quantity -14500 Week Gross requirements Scheduled receipts Projected ending inventory: 8,000 Net requirements Planned receipts Planned orders 61 2500 CD-ROM drivers Lead Time 11 weeks; Minimum order quantity -7000 Week iGross requirements Scheduled receipts Projected ending inventory: 9,500 Net requirements Planned receipts iPlanned orders 6 Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information Production plans for complete kits are as follows Start assembling 5,500 kits in week 2 Start assembling 4,000 kits in weeks 3, 4, and 5 Start assembling 16,500 kits in week 6 The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements All scheduled receipts, lead times, and beginning inventory levels are shown. EB Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers) System unit: Lead Time (weeks)-1 Week Gross requirements Scheduled receipts Projected ending inventory: 8000 INet requirements Planned receipts Planned orders Minimum order qty 16,500 5,500 4,000 4,000 4,000 16,500! iSpeakers: Lead Time- 11 Weeks Minimum order quantity -14500 Week Gross requirements Scheduled receipts Projected ending inventory: 8,000 Net requirements Planned receipts Planned orders 61 2500 CD-ROM drivers Lead Time 11 weeks; Minimum order quantity -7000 Week iGross requirements Scheduled receipts Projected ending inventory: 9,500 Net requirements Planned receipts iPlanned orders 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!