Question: Construct the network for this project, identify the critical path, and determine the project duration time. 9.17. The following probabilistic activity time estimates are for
Construct the network for this project, identify the critical path, and determine the project duration time.
9.17. The following probabilistic activity time estimates are for the network in Problem 9.6:
| Time Estimates (Months) | |||
| Activity | a | m | b |
| 1 | 4 | 8 | 12 |
| 2 | 6 | 10 | 15 |
| 3 | 2 | 10 | 14 |
| 4 | 1 | 4 | 13 |
| 5 | 3 | 6 | 9 |
| 6 | 3 | 6 | 18 |
| 7 | 2 | 8 | 12 |
| 8 | 9 | 15 | 22 |
| 9 | 5 | 12 | 21 |
| 10 | 7 | 20 | 25 |
| 11 | 5 | 6 | 12 |
| 12 | 3 | 8 | 20 |
Determine the following:
a. Expected activity times
b. Earliest start and finish times
c. Latest start and finish times
d. Activity slack
e. Critical path
f. Expected project duration and standard deviation