Question: Construct the network using the AON methodology Activity Predecessor Most Optimistic Most likely Most Pessimistic Time in days A _ 4 8 24 B _
Construct the network using the AON methodology
| Activity | Predecessor | Most Optimistic | Most likely | Most Pessimistic |
| Time in days | ||||
| A | _ | 4 | 8 | 24 |
| B | _ | 3 | 10 | 11 |
| C | _ | 6 | 12 | 24 |
| D | A;b | 9 | 14 | 25 |
| E | B;C | 11 | 16 | 27 |
| F | D;E | 13 | 15 | 35 |
| G | F | 5 | 9 | 19 |
| H | G | 7 | 15 | 23 |