Question: () Construct the project network. (Submit a file with a maximum size of 1MB.) Ne lile chesen Screenshot 2023-03-27 181852,png (b) Based solely on the

() Construct the project network. (Submit a file with a maximum size of 1MB.) Ne lile chesen Screenshot 2023-03-27 181852,png (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) 3 (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) 14 (d) Should you use the estimate in (b) or (c)? The probatility estimate from (b) based on the critical path is more accurate. The probability estimate from (c) based on both paths is more accurate. The probability estimates from (b) and (c) are equal