Question: Construction Project Example Consider the construction project defined by the precedence table and the AON network diagram below. table [ [ Activity , Predecessor,Duration

Construction Project Example
Consider the construction project defined by the precedence table and the AON network diagram below.
\table[[Activity,Predecessor,Duration (days)],[A,--,8],[B,--,10],[C,A,3],[D,A, B,7],[E,A, B,6],[F,C,7],[G,D, F,5],[H,E, G,3]]
1 point
The critical (i.e., the longest) path is
Start A C F G >H End
Start B-> D G H-> End
Start -> B -> E --> H --> End
Start A-->H H End
3
1 point
How long will it take to complete this project (in cirys)?
25
26
23
17
19
 Construction Project Example Consider the construction project defined by the precedence

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!