Question: Given the activities, predecessors, and durations displayed in the provided precedence table, draw a schedule network diagram. Please do not upload your completed diagram. It
Given the activities, predecessors, and durations displayed in the provided precedence table, draw a schedule network diagram. Please do not upload your completed diagram. It will help you in identifying network paths and answering related questions. Please use space below to answers questions a) to f). Show all your work.
a) Identify all network diagram pathways and their durations.
b) What is/are the critical path(s) and its/their duration?
c) How long will it take to complete the project?
d) What is the float (slack) time for activity K?
e) What is the float (slack) time for activity D?
f) What is the float (slack) time for activity J?
Precedence Table
| Activity (Task) | Predecessor Activity | Duration (Days) |
| A | None | 1 |
| B | C | 3 |
| C | None | 2 |
| D | A & B | 5 |
| E | C & B | 10 |
| F | None | 9 |
| G | E & F | 7 |
| H | G & J | 8 |
| I | H & J | 11 |
| J | None | 4 |
| K | I | 6 |
| L | D | 12 |