Question: consulting load if you can split operations. d, 10 Given the following AOA network for a stock repurchase project with outside consulting resource demands, construct


consulting load if you can split operations. d, 10 Given the following AOA network for a stock repurchase project with outside consulting resource demands, construct a modified Gantt chart with resources and a resource load diagram. Suggest how you might level the outside 2 , 10 f, 15 8 1, 10 6\f