Question: Given the following network for a stock repurchase project with outside consulting resource demands, construct a modified Gantt AOA chart with resources and a resource
.png)
Code activity, time resource units d, 10 , 15 g, 10
Step by Step Solution
3.34 Rating (178 Votes )
There are 3 Steps involved in it
In Figure a the peak resource load is 26 units beginning on September 4 th and ending on September 1... View full answer