Question: content area Part 1 A project organization: Part 2 A. is effective for companies with multiple large projects. B. is most helpful for ongoing projects
content area Part 1 A project organization: Part 2 A. is effective for companies with multiple large projects. B. is most helpful for ongoing projects with no termination date. C. often fails when the project cuts across organizational lines. D. is most helpful when the work contains simple and unrelated tasks. E. is appropriate only in construction firms