Question: Continuous Flow - One - at - a - time with Setup and Batching: Consider a single - machine station fabricating a part as follows:

Continuous Flow - One-at-a-time with Setup and Batching: Consider a single-machine station fabricating a part as follows: The station produces parts one-at-a-time in batches of Q units, where Q is specified (known). Every time a batch of Q units of the product is produced, there is a fixed setup time S and a batch processing time of Q x t, where t = unit process time for one part.
Write an expression for the maximum throughput, TH = rb, and minimum average cycle time, CT = T0, for this single-machine, single-station line. What would be the critical WIP W0 for this line? Your answers should be in terms of parameters S, Q, and t.
Suppose S =2 hours, Q =10, t =1 hour, calculate the value of the critical WIP W0 for this line.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!