Question: Contract requirements state that a project must be completed within 150 working days, or it will incur penalties for late completion. Analysis of the activity
Contract requirements state that a project must be completed within 150 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 175 working days with a project variance of 300. What is the probability that the project will be completed before the late-payment deadline?