Question: Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 155 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
A. 0.89435
B. near 1.00000, or almost certain
C. 0.45994
D. 0.95994
E. 0.04006
Step by Step Solution
There are 3 Steps involved in it