Question: Control Charts - Assignment Info You will see two control charts on the next two slides Slide 2 - Control Chart - Percentage of Schedule

Control Charts - Assignment Info
You will see two control charts on the next two slides
Slide 2- Control Chart - Percentage of Schedule Attainment
This is an actual control chart showing the percentage of a production schedule for half-shaft assemblies that was achieved per day
The target value (set by the Executive Management) for daily schedule attainment was 85%, which from historical data showed that both unplanned overtime expense and premium freight expense would be avoided
Slide 3- Control Chart - March Paint Products
This is an actual control chart showing the daily output in units painted from March Paint Products
The target value for daily painted units was 30,000 per day. On 813, they began using QAD schedules to schedule the units to be painted. QAD is a software, much like SAP, that has Material Requirements Planning (MRP) built into it, which enables scheduling of the painted units.
 Control Charts - Assignment Info You will see two control charts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!