Question: conveyor belt project Each work package will represent an activity. The project begins January 5 , 2 0 2 6 . The following holidays are
conveyor belt project Each work package will represent an activity.
The project begins January
The following holidays are observed: January Memorial Day last Monday in May July th Labor Day first Monday in September Thanksgiving Day fourth Thursday in November December
If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.
The project teams work eighthour days, Monday through Friday.
Warning: Experience has taught students to frequently make separate backup files for each exercise. The software is never as friendly as users expect!
Construct a network schedule for the conveyor belt project and prepare a memo that addresses the following questions:
When is the project estimated to be completed? How long will the project take?
What is the critical paths for the project?
Which activity has the greatest amount of slack?
How sensitive is this network?
Identify two sensible milestones and explain your choices.
Compare the advantagesdisadvantages of displaying the schedule as a network versus a Gantt chart.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock