Question: correct answer please A company is designing a product layout for a new product. It plans to use this production line eight hours a day
correct answer please
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product: TASK PREDECESSOR TIME (Seconds) u v u w u X Y W X z vy 533 O 480 O 420 30 O 600 30 6 What is the maximum production output that can be expected? 12 54 30