Question: correct answer please Using the work breakdown structure (WBS) shown below answer ALL the following questions. 1.00.00 begin{tabular}{llll} 1.1.0 & multicolumn{1}{c}{($25K)} & 1.1.1 &

correct answer please
Using the work breakdown structure (WBS) shown below answer ALL the following questions. 1.00.00 \begin{tabular}{llll} 1.1.0 & \multicolumn{1}{c}{($25K)} \\ & 1.1.1 & & \\ & 1.1.2 & ($12K) \\ 1.2.0 & & \\ & 1.2.1 & ($15K) \\ & 1.2.2.0 & \\ & & 1.2.2.1 & ($15K) \\ & & 1.2.2.2 & ($20K) \end{tabular} The cost of WBS element 1.2.2.0 is: a. $20K b. $35K c. $50K d. Cannot be determined QUESTION 43 The cost of WBS element 1.1.1 is: a. $18K Click Save and Submit to save and submit. Chick Save All Answers to save all answersStep by Step Solution