Question: using project tracking program and screenot the answer Q.1) Draw Work Breakdown Structure ( WBS ) for Bank Management System project using the activities listed
using project tracking program and screenot the answer
Q.1) Draw Work Breakdown Structure (WBS) for Bank Management System project using the activities listed below. (5 Marks)
- Initiation
1.1.1 Develop Business Case
1.1.2 Assign Project Manager
1.1.3 Develop Project Charter
1.2 Planning
1.2.1 Develop Project Management Plan
1.2.2 Develop WBS
1.2.3 Develop Schedule
1.3 Execution & Control
1.3.1 Manage Communication
1.3.2 Execute Project Task
1.3.3 Manage changes
1.3.4 Approve changes
1.4 Close Out
1.4.1 Document the project
1.4.2 Install project
1.4.3 Lessons learnt
1.4.4 Close project
Q.2) Draw Gantt Chart using the following table that related to develop new project for certain local company. (5 Marks)
| Task | Duration (days) | Predecessor |
| Group 1 |
|
|
| Task1 | 2 |
|
| Task2 | 4 | Task1 |
| Task3 | 5 | Task2 |
| Group 2 |
|
|
| Task4 | 6 | Task3 |
| Task5 | 6 | Task4 |
| Task6 | 4 | Task5 |
| Task7 | 2 | Task6 |
| Group 3 |
|
|
| Task8 | 5 | Task7 |
| Task9 | 3 | Task8 |
| Task10 | 2 | Task9 |
| Task11 | 2 | Task9, Task 10 |
| Task12 | 1 | Task11 |
Q3.) A project involving the installation of a new information system consists of 8 activities. The information about activities is shown in the table below. Answer the following questions:
| Activity | Predecessor | Duration (Days) |
| A | - | 3 |
| B | A | 5 |
| C | A | 2 |
| D | B | 5 |
| E | B and C | 3 |
| F | C, D | 4 |
| G | D, E | 5 |
| H | , G | 3 |
- Draw network diagram (4 Marks)
Find the critical path