Question: using project tracking program and screenot the answer Q.1) Draw Work Breakdown Structure ( WBS ) for Bank Management System project using the activities listed

using project tracking program and screenot the answer

Q.1) Draw Work Breakdown Structure (WBS) for Bank Management System project using the activities listed below. (5 Marks)

  1. Initiation

1.1.1 Develop Business Case

1.1.2 Assign Project Manager

1.1.3 Develop Project Charter

1.2 Planning

1.2.1 Develop Project Management Plan

1.2.2 Develop WBS

1.2.3 Develop Schedule

1.3 Execution & Control

1.3.1 Manage Communication

1.3.2 Execute Project Task

1.3.3 Manage changes

1.3.4 Approve changes

1.4 Close Out

1.4.1 Document the project

1.4.2 Install project

1.4.3 Lessons learnt

1.4.4 Close project

Q.2) Draw Gantt Chart using the following table that related to develop new project for certain local company. (5 Marks)

Task

Duration (days)

Predecessor

Group 1

Task1

2

Task2

4

Task1

Task3

5

Task2

Group 2

Task4

6

Task3

Task5

6

Task4

Task6

4

Task5

Task7

2

Task6

Group 3

Task8

5

Task7

Task9

3

Task8

Task10

2

Task9

Task11

2

Task9, Task 10

Task12

1

Task11

Q3.) A project involving the installation of a new information system consists of 8 activities. The information about activities is shown in the table below. Answer the following questions:

Activity

Predecessor

Duration (Days)

A

-

3

B

A

5

C

A

2

D

B

5

E

B and C

3

F

C, D

4

G

D, E

5

H

, G

3

  1. Draw network diagram (4 Marks)

Find the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!