Question: Cost Account Planned Value Earned Value Actual Cost 1 . 2 . 1 $ 2 7 5 $ 3 0 0 $ 3 7 5
Cost Account
Planned Value
Earned Value
Actual Cost
$
$
$
$
$
$
Figure
Based on the data in Figure above, Cost Account is of schedule and cost
Group of answer choices
On under
Ahead, over
Ahead, on
Behind, under
Behind, over