Question: Cost Account Planned Value Earned Value Actual Cost 1 . 2 . 1 $ 3 5 0 $ 3 5 0 $ 3 0 0

Cost Account
Planned Value
Earned Value
Actual Cost
1.2.1
$350
$350
$300
1.3.1
$200
$150
$175
Figure 1
32. Based on the data in Figure 1 above, Cost Account 1.2.1 is _____(of) schedule and _____ cost
Group of answer choices
Behind, under
Ahead, on
On, under
Behind, over
Ahead, over