Cost Performance Report 1. This exercise requires you to complete the Earned Value Analysis for the...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Cost Performance Report 1. This exercise requires you to complete the Earned Value Analysis for the 1st, 3rd, and 5th Reporting Periods. You must provide the: a. Planned Value b. Earned Value for each work activity c. Total Earned Value d. Schedule Variance & Cost Variance (Show all work) e. Schedule Performance Indicator & Cost Performance Indicator (Show all work) 2. Respond to the following questions: a. Based on the documented information what is the Estimate at Completion (EAC) b. What is the To Complete Performance Index C. Is there enough available budget to complete the remaining work? 1st REPORTING PERIOD: Percent Start/Percent Finish WBS Budget 2 3 1.1.1 $6,216 3,108 3,108 1.1.2 $6,216 3,108 3,108 1.2.1 $2,960 1,480 1,480 1.2.2 $740 740 1.3.1 $10,560 5,280 5,280 1.3.2 $2,910 1,455 1,455 1.4.1 $10,886 5,443 5,443 1.4.2 $7,666 7,666 1.5.1 $3,520 1,760 1,760 TOTAL $51,674 $4,588 88 $4, $4,588 $9,128 $9,843 $16,324 $ $7,203 Cumulative PV $4,588 $9,716 $18,304 $28,147 $44,471 $51,674 PV = $ 1st Reporting Period: Activity 1.1.1 - 50% Complete Activity 1.1.2- EV = $ EV = $ AC = $3,108 AC= $ Activity 1.2.1 - 50% Complete EV = $ AC = $1,480 Activity 1.2.2- EV = $ AC = $ Activity 1.3.1- EV = $ AC = $ Activity 1.3.2- EV = $ AC = $ Activity 1.4.1- EV = $ AC = $ Activity 1.4.2 - EV = $ AC = $ Activity 1.5.1- EV = $ AC=$ EV = $ AC = $ SV = SV = $ EV - - - $ PV = $ CV = CV = $ EV - AC - $ = $ 3rd REPORTING PERIOD Percent Start/Percent Finish WBS Budget 1.1.1 $6,216 3,108 3,108 1.1.2 $6,216 3,108 3,108 1.2.1 $2,960 1,480 1,480 1.2.2 $740 740 1.3.1 $10,560 5,280 5,280 1.3.2 $2,910 1,455 1,455 1.4.1 $10,886 5,443 5,443 1.4.2 $7,666 7,666 1.5.1 $3,520 1,760 1,760 TOTAL $51,674 $4,588 $4,588 88 $9 $9,128 $9,843 $16,324 $7,203 5th REPORTING PERIOD Percent Start/Percent Finish WBS Budget 1.1.1 $6,216 3,108 3,108 1.1.2 $6,216 3,108 3,108 1.2.1 $2,960 1,480 1,480 1.2.2 $740 740 1.3.1 $10,560 5,280 5,280 1.3.2 $2,910 1,455 1,455 1.4.1 $10,886 5,443 5,443 1.4.2 $7,666 7,666 1.5.1 $3,520 1,760 1,760 TOTAL $51,674 $4,588 $4,588 $9,128 $9,843 $16,324 $7,203 Cumulative PV $4,588 $9,716 $18,304 $28,147 $44,471 $51,674 5th Reporting Period: Activity 1.1.1 - Complete EV = $ AC = $6,216 PV = $ Activity 1.1.2-90% Complete Activity 1.2.1 - Complete EV = $ AC= $5,594 EV = $ AC = $2,960 Activity 1.2.2 - 85% Complete EV = $ AC = $ 629 Activity 1.3.1-60% Complete EV = $ AC = $6,336 Activity 1.3.2-50% Complete EV = $ AC = $1,455 Activity 1.4.1-75% Complete EV = $ AC = $8,165 Cost Performance Report 1. This exercise requires you to complete the Earned Value Analysis for the 1st, 3rd, and 5th Reporting Periods. You must provide the: a. Planned Value b. Earned Value for each work activity c. Total Earned Value d. Schedule Variance & Cost Variance (Show all work) e. Schedule Performance Indicator & Cost Performance Indicator (Show all work) 2. Respond to the following questions: a. Based on the documented information what is the Estimate at Completion (EAC) b. What is the To Complete Performance Index C. Is there enough available budget to complete the remaining work? 1st REPORTING PERIOD: Percent Start/Percent Finish WBS Budget 2 3 1.1.1 $6,216 3,108 3,108 1.1.2 $6,216 3,108 3,108 1.2.1 $2,960 1,480 1,480 1.2.2 $740 740 1.3.1 $10,560 5,280 5,280 1.3.2 $2,910 1,455 1,455 1.4.1 $10,886 5,443 5,443 1.4.2 $7,666 7,666 1.5.1 $3,520 1,760 1,760 TOTAL $51,674 $4,588 88 $4, $4,588 $9,128 $9,843 $16,324 $ $7,203 Cumulative PV $4,588 $9,716 $18,304 $28,147 $44,471 $51,674 PV = $ 1st Reporting Period: Activity 1.1.1 - 50% Complete Activity 1.1.2- EV = $ EV = $ AC = $3,108 AC= $ Activity 1.2.1 - 50% Complete EV = $ AC = $1,480 Activity 1.2.2- EV = $ AC = $ Activity 1.3.1- EV = $ AC = $ Activity 1.3.2- EV = $ AC = $ Activity 1.4.1- EV = $ AC = $ Activity 1.4.2 - EV = $ AC = $ Activity 1.5.1- EV = $ AC=$ EV = $ AC = $ SV = SV = $ EV - - - $ PV = $ CV = CV = $ EV - AC - $ = $ 3rd REPORTING PERIOD Percent Start/Percent Finish WBS Budget 1.1.1 $6,216 3,108 3,108 1.1.2 $6,216 3,108 3,108 1.2.1 $2,960 1,480 1,480 1.2.2 $740 740 1.3.1 $10,560 5,280 5,280 1.3.2 $2,910 1,455 1,455 1.4.1 $10,886 5,443 5,443 1.4.2 $7,666 7,666 1.5.1 $3,520 1,760 1,760 TOTAL $51,674 $4,588 $4,588 88 $9 $9,128 $9,843 $16,324 $7,203 5th REPORTING PERIOD Percent Start/Percent Finish WBS Budget 1.1.1 $6,216 3,108 3,108 1.1.2 $6,216 3,108 3,108 1.2.1 $2,960 1,480 1,480 1.2.2 $740 740 1.3.1 $10,560 5,280 5,280 1.3.2 $2,910 1,455 1,455 1.4.1 $10,886 5,443 5,443 1.4.2 $7,666 7,666 1.5.1 $3,520 1,760 1,760 TOTAL $51,674 $4,588 $4,588 $9,128 $9,843 $16,324 $7,203 Cumulative PV $4,588 $9,716 $18,304 $28,147 $44,471 $51,674 5th Reporting Period: Activity 1.1.1 - Complete EV = $ AC = $6,216 PV = $ Activity 1.1.2-90% Complete Activity 1.2.1 - Complete EV = $ AC= $5,594 EV = $ AC = $2,960 Activity 1.2.2 - 85% Complete EV = $ AC = $ 629 Activity 1.3.1-60% Complete EV = $ AC = $6,336 Activity 1.3.2-50% Complete EV = $ AC = $1,455 Activity 1.4.1-75% Complete EV = $ AC = $8,165
Expert Answer:
Related Book For
Intermediate Algebra
ISBN: 9780134895987
13th Edition
Authors: Margaret Lial, John Hornsby, Terry McGinnis
Posted Date:
Students also viewed these general management questions
-
This assignment requires you to complete the 2022 tax reporting for a fictional woman named Anna Smith. Question 1 T1 - step 4 - line 66 This is Anna's taxable income Answer: Question 2 T1 - step...
-
THIRD AVENUE SOFTWARE HEALTH-CARE APP PROJECT This case is new for the ninth edition of Information Technology Project Management . The case provides an opportunity to apply agile and Scrum...
-
a. Firm A has a margin of 14%, sales of $640,000, and ROI of 18%. Calculate the firm's average total assets. b. Firm B has net income of $72,000, asset turnover of 1.40, and average total assets of...
-
A charged particle is caused to move between two electrically charged plates, as shown here. (a)Why does the path of the charged particle bend? (b)What is the sign of the electrical charge on the...
-
What are the precedents (research) about the Fed's bailout? Include two links to research related to when the Fed has invoked emergency powers.
-
Identify and explain the purpose of each of the four perspectives included in the balanced scorecard. Give two examples of HR measures for each of the four areas that would demonstrate the value of...
-
Xellnet provides e- commerce software for the pharmaceuticals industry. Xellnet is orga-nized into several divisions. A companywide planning committee sets general strategy and goals for the company...
-
Calculate the current in each resistor in the following Network. What is the Potential difference voltage across the 50 resistor? 50 10 10 V 40 30
-
1. A 10-ft-tall concrete wall with a vertical back is to be backfilled with a silty sand that has a unit weight of 122 lb/ft3, an effective friction angle of 32, and no cohesion. The ground behind...
-
Which of the following represents an actor? (a) An individual user (b) A role (c) An operation (d) A flow
-
What is the primary purpose of the first stage of software analysis and design? (a) Determining system deployment (b) Writing code (c) Capturing requirements (d) Building GUIs
-
Explain the relationships among the price of a product in a perfectly competitive market, the average revenue of a firm in that market, and its marginal revenue.
-
Which of the following statements is true of actors? (i) One person cannot be a number of different actors. (ii) Use cases are initiated by actors. (iii) An actor is an instance of a class. (iv) An...
-
Identify each of the distinct ways in which an actor can interact with the system. (i) An actor can input information into the system (ii) An actor can receive information from the system (iii) An...
-
The IRS reports that the mean refund for a particular group of taxpayers was $1,600. The distribution of tax refunds follows a normal distribution with a standard deviation of $850. a. What...
-
The graph of the sequence whose general term is an = n - 1 is which of the following? [8.1] A. B. TITTT 3-2-1 23.45 2.3.4
-
What is the change in velocity of \((a)\) cart 1 (b) cart 2 in Figure 4.6? (c) What do you notice about your two answers? Figure 4.6 Velocity-versus-time graph for two identical carts before and...
-
(a) Are the accelerations of the motions shown in Figure 4.1 constant? (b) For which surface is the acceleration largest in magnitude? Figure 4.1 Velocity-versus-time graph for a wooden block sliding...
-
The \(x\) component of the final velocity of the standard cart in Figure 4.8 is positive. Can you make it negative by adjusting this cart's initial speed while still keeping the half cart initially...
Study smarter with the SolutionInn App