Question: Cost (S) Duration per Resource Hours Activity (days) Predecessors machine per Day A 1 x 1000 3 B 2 A 250 6 c 3 A


Cost (S) Duration per Resource Hours Activity (days) Predecessors machine per Day A 1 x 1000 3 B 2 A 250 6 c 3 A 500 4 o 5 B.C 600 7 E 6 B, D 300 5 F 4 c,D 400 5 G 10 A 1200 8 H 2 E.F, G 1200 2