Question: Costs related to _ _ _ _ _ _ _ _ _ _ _ are for outsourced work when the project teams or contractors do
Costs related to are for outsourced work when the project teams or contractors do not have the expertise or resources to do certain project tasks.
Group of answer choices
benefactors and suppliers
stakeholders
reserve and withholding
subcontractors and consultants